Project Salient Features
Name of the Project Varanasi-Ranchi-Kolkata Highway Pkg-13
Description of the Project Construction of 6-lane Greenfield Varanasi-Ranchi-Kolkata Highway from junction with NH-320 in Lepo village to Kamlapur village (JH/WB border) from km 358.500 to km 387.200 under Bharatmala Pariyojana in the State of Jharkhand on Hybrid Annuity Mode.
Authority NHAI
Scheme Bharatmala Pariyojana
Mode of Implementation Hybrid Annuity Mode
Name of NH Varanasi-Ranchi-Kolkata Highway
Name of Concessionaire H.G. Varanasi Kolkata Pkg-13 Private Limited
Date of LOA 31st March 2023
Date of signing of Agreement 28th June 2023
Appointed Date 30th September 2025
Scheduled completion date 30th September 2027
Likely completion date 30th June 2027
Construction Period 730 Days
O&M Period 15 Years
Length of Project 28.70 Km
Bid Project cost Rs. 925.11 Cr.
Sanctioned cost
Total Capital Cost
Independent Engineer L.N. Malviya Infra Projects
Deployment of IE 05/06/2024
Contract Amount of IE
Scheduled Completion of IE Tenure 30th September 2027
Safety Consultant Road Link Consultancy Services
Date of deployment 03/02/2024
Contract Amount
Tenure Upto
Physical Progress (Till Date) 4%
Financial Progress 2.50%
Expenditure (payment to concessionaire)