JH-13 Project Milestone
Project Milestone Days from Appointed Date
Milestone-01 20% within 180 Days
Milestone-02 35% within 360 Days
Milestone-03 75% within 550 Days
Milestone-04 100% within 730 Days
Status of Highway work:
S.No. Items Scope (in Km) Completed (in Km) Balance (in Km) Remarks
1 C&G 54.99 30.88 24.11
2 Embankment Top 54.99 6.07 48.92
3 Subgrade Top 54.99 5.14 49.85
4 GSB 54.99 1.96 53.03
5 WMM 54.5 0 54.5
6 DBM 54.5 0 54.5
7 SMA 54.5 0 54.5
Status of Structures:
S.No. Items Total No. of Structures Status Balance
1 Major Bridge 1
2 Minor Bridge 14 03 nos. WIP
3 Minor Bridge cum Wildlife Crossing 1
4 Minor Bridge cum Underpass 1
5 Culverts 54+20 Additional 19 Nos. location WIP ( 08 Nos erection completed)
6 Viaduct 2 01 Nos WIP
7 VUPs 1 01 Nos WIP
8 VOPs 1 01 Nos WIP
9 LVUPs 18 11 nos WIP (1.5 Nos Slab completed)
10 SVUPs 4 4 NOS. WIP
11 Str. Over Gas Pipe Line 1 01 Nos WIP
12 AUPs NA
13 Monket Canopies NA
14 Interchanges NA
15 Way Side Amenities NA
16 ROB NA