JH-13 Project Milestone
Project Milestone Days from Appointed Date
Milestone-01 20% within 180 Days
Milestone-02 35% within 360 Days
Milestone-03 75% within 550 Days
Milestone-04 100% within 730 Days
Status of Highway work:
S.No. Items Scope (in Km) Completed (in Km) Balance (in Km) Remarks
1 C&G 55.18 15.37 39.81 50.102/159.952 Hact.
2 Embankment Top 55.18 1.940 53.240
3 Subgrade Top 55.18 1.750 53.430
4 GSB 55.18 55.18
5 DBM 55.18 55.18
6 SMA 55.18 55.18
Status of Structures:
S.No. Items Total No. of Structures Status Balance
1 Major Bridge 1
2 Minor Bridge 14 02 nos. WIP
3 Minor Bridge cum Wildlife Crossing 1
4 Minor Bridge cum Underpass 1
5 Culverts 74 10 Nos. location WIP
6 Viaduct 2
7 VUPs 1
8 VOPs 1
9 LVUPs 18 6 nos WIP
10 SVUPs 4 2 NOS. WIP
11 Str. Over Gas Pipe Line 1
12 AUPs NA
13 Monket Canopies NA
14 Interchanges NA
15 Way Side Amenities NA
16 ROB NA